HS2 completes tunnel link into Old Oak Common station

HS2 tunnellers have broken through into Old Oak Common station, connecting it to the line that will eventually carry trains from London to Birmingham.

The breakthrough creates an 8.8-mile underground connection between the station and West Ruislip. Teams excavated two 360-metre tunnels from the Victoria Road crossover box, removing 100,000 tonnes of London clay.

Work began in May 2024. The northbound tunnel reached the station last month (13 October 2026), with the latest breakthrough completing the connection. These sections were dug using excavators rather than the tunnel boring machines used elsewhere on the line.

The new HS2 station is not expected to be used by passengers for at least another decade.

As EALING.NEWS reported in May 2026, the government expects services between Old Oak Common and Birmingham to begin between 2036 and 2039 following a reset of the project.

Old Oak Common will initially be HS2’s London terminus, where passengers can change for the Elizabeth line and other rail services. The extension to Euston is not expected to be completed until between 2040 and 2043.

Two boring machines are currently digging the 4.5-mile route from Old Oak Common towards Euston and are expected to finish tunnelling in mid-2027.

Transport Secretary Heidi Alexander said in May 2026 that HS2 had suffered from years of “mismanagement, flawed reporting and ineffective oversight”. The government said projected costs had risen to as much as £102.7 billion.

Are you an Ealing resident with a story to share? Or spotted something we should know about?
Get in touch with us by emailing: news@ealing.news or contact us on X @_EalingNews

SUBSCRIBE FOR FREE TO THE EALING.NEWS NEWSLETTER

GET OUR GREAT NEWS, FEATURES, REVIEWS AND MORE DIRECT TO YOUR INBOX

SUPPORT JOURNALISM IN EALING

LATEST EALING.NEWS UPDATES

MORE FROM EALING.NEWS